WE Report

Lessons Learned

Lesson Learned





By: Drilling Engineer

Report No.

4906

Discipline/Origin

Drilling
No origin

Well

Copernicus
6608/1-1 S

Date created

2022/09/16
1178 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Operational
N/A

Deepsea Yantai


What happened in Top hole:
30″ conductor was run as a “pre spud” activity. Hung off in landing string and acme sub in trip saver.

What Was Learned

Good time saving potential, but Drill-Quip forgot to install av plate on the running tool. This resulted in that we had to pull out the string again on critical timeline, and install the plate before running the conductor. Lost time at least 2 hrs.

What Actions Are Required

Drill quip to update their procedure, so this incident don`t happen again.